Kerepēhi Raw Water Upgrades

Share Kerepēhi Raw Water Upgrades on Facebook Share Kerepēhi Raw Water Upgrades on Twitter Share Kerepēhi Raw Water Upgrades on Linkedin Email Kerepēhi Raw Water Upgrades link




Kerepēhi will be busy over the next 12 months with construction of two new raw water storage reservoirs at the water treatment plant and the replacement of the existing main from the Pekapeka intake on Hauraki Road.



Raw Water Storage Reservoirs

The new reservoirs, due for completion mid-year, will add around 4 million litres additional storage. This will significantly reduce the risk of a raw water shortage that can occur in severe weather events and due to the tidal influence of the source water (Waihou river).

The water treatment plant will have around 24 hours reserve of raw water at current processing throughput.

This will enable the network to be continuously supplied, increasing the resilience of the water supply network without loss of service.

The budget for this project is approximately $2.7 million and will be constructed by Reliant Solution Limited who also constructed the two treated water storage reservoirs at the site in 2018.

The tanks will be constructed simultaneously at the back of the treatment plant. The civil works on the new reservoirs are scheduled to start late March but the level of activity on site will slowly increase from the beginning of the month.

Another important part of the project is to extend the new raw water rising main to feed the new storage reservoirs.


Raw Water Main

Work is already underway to replace the current 450mm-diameter pipe from the Pekapeka intake to the Kerepēhi water treatment plant.

These pipes have reached their end of life. The renewals will increase resilience in the network and provide security of the supply.

A total of 5.3 kilometres of a 630mm-diameter raw water intake pipe is being laid which will connect to the two new raw water storage tanks. Budget for the pipeline is $6.05 million.



We will be posting regular updates throughout the Kerepēhi Raw Water upgrades right here. You can also keep up with the latest news throughout the Hauraki District by signing up for our newsletters.




Kerepēhi will be busy over the next 12 months with construction of two new raw water storage reservoirs at the water treatment plant and the replacement of the existing main from the Pekapeka intake on Hauraki Road.



Raw Water Storage Reservoirs

The new reservoirs, due for completion mid-year, will add around 4 million litres additional storage. This will significantly reduce the risk of a raw water shortage that can occur in severe weather events and due to the tidal influence of the source water (Waihou river).

The water treatment plant will have around 24 hours reserve of raw water at current processing throughput.

This will enable the network to be continuously supplied, increasing the resilience of the water supply network without loss of service.

The budget for this project is approximately $2.7 million and will be constructed by Reliant Solution Limited who also constructed the two treated water storage reservoirs at the site in 2018.

The tanks will be constructed simultaneously at the back of the treatment plant. The civil works on the new reservoirs are scheduled to start late March but the level of activity on site will slowly increase from the beginning of the month.

Another important part of the project is to extend the new raw water rising main to feed the new storage reservoirs.


Raw Water Main

Work is already underway to replace the current 450mm-diameter pipe from the Pekapeka intake to the Kerepēhi water treatment plant.

These pipes have reached their end of life. The renewals will increase resilience in the network and provide security of the supply.

A total of 5.3 kilometres of a 630mm-diameter raw water intake pipe is being laid which will connect to the two new raw water storage tanks. Budget for the pipeline is $6.05 million.



We will be posting regular updates throughout the Kerepēhi Raw Water upgrades right here. You can also keep up with the latest news throughout the Hauraki District by signing up for our newsletters.

  • Raw Water Storage Reservoirs - 13 November 2024

    Share Raw Water Storage Reservoirs - 13 November 2024 on Facebook Share Raw Water Storage Reservoirs - 13 November 2024 on Twitter Share Raw Water Storage Reservoirs - 13 November 2024 on Linkedin Email Raw Water Storage Reservoirs - 13 November 2024 link

    Just a few weeks ago the foundations were poured.....so much progress in such a short time!

    This was on November 5th.....

    Let's just sneak in a pretty spectacular night shot.....

    And fast forward to today.....




  • Raw Water Storage Reservoirs Update - 31 October 2024

    Share Raw Water Storage Reservoirs Update - 31 October 2024 on Facebook Share Raw Water Storage Reservoirs Update - 31 October 2024 on Twitter Share Raw Water Storage Reservoirs Update - 31 October 2024 on Linkedin Email Raw Water Storage Reservoirs Update - 31 October 2024 link

    The foundations for the Raw Water Storage Reservoirs are reinforced and pouring of the concrete started at 5am this morning!

    Above: Reinforcement of the foundations underway.

    Above: One foundation poured, one to go!

    Each foundation will take a total of 80m3 of concrete - that's 18 truckloads!


















  • Raw Water Storage Reservoirs Update - 12 August 2024

    Share Raw Water Storage Reservoirs Update - 12 August 2024 on Facebook Share Raw Water Storage Reservoirs Update - 12 August 2024 on Twitter Share Raw Water Storage Reservoirs Update - 12 August 2024 on Linkedin Email Raw Water Storage Reservoirs Update - 12 August 2024 link


    Work is underway on the foundations for the Raw Water Storage Reservoirs at the Kerepēhi Water Treatment Plant.

    358 individual piles will be drilled down 5 metres to support the weight of the two new reservoirs.

    The new reservoirs will store an additional 4 million litres of raw water.

  • Raw Water Main Renewal Update - 22 April 2024

    Share Raw Water Main Renewal Update - 22 April 2024 on Facebook Share Raw Water Main Renewal Update - 22 April 2024 on Twitter Share Raw Water Main Renewal Update - 22 April 2024 on Linkedin Email Raw Water Main Renewal Update - 22 April 2024 link


    Above: The red and blue line is the water main which has been replaced.The majority of the new raw water main from the Pekapeka intake to Kerepēhi Water Treatment Plant (WTP) has been laid.


    Our contractors, Camex Civil, have been flat out installing approximately 180m per day.


    Work this week will include drilling under State Highway 2.


    Next week work will be starting from the highway heading west towards the WTP (the blue dotted line above).

Page last updated: 13 Nov 2024, 02:04 PM