District Wide Water Supply Pipe Renewals
Consultation has concluded

The District Wide Water Supply Pipe Renewals will upgrade and replace the aging water infrastructure at eight sites throughout the district. The project scheduled to run over the next two years (2024/25).
Sites scheduled for work are:
- Coronation St, Paeroa
- Thames Rd, Paeroa
- Rakino Drive, Kerepēhi
- SH25, Pipiroa
- Canal St East, Ngātea
- Opua Rd, Turua
- Wood St, Paeroa
- Hauraki Rd, Paeroa
Our contractors, Odlum Group, have been on the job since mid-February and already over 4kms of pipeline has been replaced at three sites.
We will be posting regular updates right here. You can also keep up with the latest news throughout the Hauraki District by signing up for our newsletters.

The District Wide Water Supply Pipe Renewals will upgrade and replace the aging water infrastructure at eight sites throughout the district. The project scheduled to run over the next two years (2024/25).
Sites scheduled for work are:
- Coronation St, Paeroa
- Thames Rd, Paeroa
- Rakino Drive, Kerepēhi
- SH25, Pipiroa
- Canal St East, Ngātea
- Opua Rd, Turua
- Wood St, Paeroa
- Hauraki Rd, Paeroa
Our contractors, Odlum Group, have been on the job since mid-February and already over 4kms of pipeline has been replaced at three sites.
We will be posting regular updates right here. You can also keep up with the latest news throughout the Hauraki District by signing up for our newsletters.
-
More sites now scheduled for Water Supply Pipe Renewals
Share More sites now scheduled for Water Supply Pipe Renewals on Facebook Share More sites now scheduled for Water Supply Pipe Renewals on Twitter Share More sites now scheduled for Water Supply Pipe Renewals on Linkedin Email More sites now scheduled for Water Supply Pipe Renewals linkWith all the work on the current schedule completed we're extending this project to include the following sites:
- Paeroa - Wharf Street and Norwood Road
- Turua - Main Street Upgrade and Ōrongo to Kopu Bridge
- Waihī - Haszard and Mueller Streets
- Kerepēhi - Rata Street
Keep an eye on this site and download Antenno for future updates.
Consultation has concludedWith all the work on the current schedule completed we're extending this project to include the following sites:
- Paeroa - Wharf Street and Norwood Road
- Turua - Main Street Upgrade and Ōrongo to Kopu Bridge
- Waihī - Haszard and Mueller Streets
- Kerepēhi - Rata Street
Keep an eye on this site and download Antenno for future updates.
-
Canal West to East, Waitakaruru - Complete
Share Canal West to East, Waitakaruru - Complete on Facebook Share Canal West to East, Waitakaruru - Complete on Twitter Share Canal West to East, Waitakaruru - Complete on Linkedin Email Canal West to East, Waitakaruru - Complete linkApproximately 175m of watermain, 2 new service connections and valves are scheduled for this site.
Consultation has concludedApproximately 175m of watermain, 2 new service connections and valves are scheduled for this site.
-
Rakino Drive, Kerepehī - Complete
Share Rakino Drive, Kerepehī - Complete on Facebook Share Rakino Drive, Kerepehī - Complete on Twitter Share Rakino Drive, Kerepehī - Complete on Linkedin Email Rakino Drive, Kerepehī - Complete linkThis work is now complete.
Approximately 485m of watermain, 14 new service connections, valves and hydrants is scheduled to be installed.
Consultation has concludedThis work is now complete.
Approximately 485m of watermain, 14 new service connections, valves and hydrants is scheduled to be installed.
-
Thames Road, Paeroa - Complete
Share Thames Road, Paeroa - Complete on Facebook Share Thames Road, Paeroa - Complete on Twitter Share Thames Road, Paeroa - Complete on Linkedin Email Thames Road, Paeroa - Complete linkThis work is now complete.
Approximately 420m of watermain including 22 new service connections, valves and hydrants is scheduled to be installed in Thames Road.
Consultation has concludedThis work is now complete.
Approximately 420m of watermain including 22 new service connections, valves and hydrants is scheduled to be installed in Thames Road.
-
Opua Road, Turua - Complete
Share Opua Road, Turua - Complete on Facebook Share Opua Road, Turua - Complete on Twitter Share Opua Road, Turua - Complete on Linkedin Email Opua Road, Turua - Complete link
Approximately 1806m of watermain including 11 new service connections and valves are scheduled for this site.
Work is underway from Bush Road to the east along Opua Road.
Consultation has concluded
Approximately 1806m of watermain including 11 new service connections and valves are scheduled for this site.
Work is underway from Bush Road to the east along Opua Road.
-
Coronation Street, Paeroa - Complete
Share Coronation Street, Paeroa - Complete on Facebook Share Coronation Street, Paeroa - Complete on Twitter Share Coronation Street, Paeroa - Complete on Linkedin Email Coronation Street, Paeroa - Complete link
Approximately 740m of watermain including 17 new connections, valves and hydrants are currently being installed on this site.
Work is underway from outside Paeroa Christian School north to the end of Coronation Street, and to the west along Opukeko Road to Henton Road.
Consultation has concluded
Approximately 740m of watermain including 17 new connections, valves and hydrants are currently being installed on this site.
Work is underway from outside Paeroa Christian School north to the end of Coronation Street, and to the west along Opukeko Road to Henton Road.
-
State Highway 25, Pipiroa - Complete
Share State Highway 25, Pipiroa - Complete on Facebook Share State Highway 25, Pipiroa - Complete on Twitter Share State Highway 25, Pipiroa - Complete on Linkedin Email State Highway 25, Pipiroa - Complete link
Approximately 1905m of new watermain including 21 new service connections, valves and hydrants are currently being laid from Pipiroa Road east to the Piako River along State Highway 25.
Consultation has concluded
Approximately 1905m of new watermain including 21 new service connections, valves and hydrants are currently being laid from Pipiroa Road east to the Piako River along State Highway 25.
-
Hauraki Road, Paeroa - Complete
Share Hauraki Road, Paeroa - Complete on Facebook Share Hauraki Road, Paeroa - Complete on Twitter Share Hauraki Road, Paeroa - Complete on Linkedin Email Hauraki Road, Paeroa - Complete link
Approximately 1347m of watermain including 12 new service connections and valves is being laid from Wharepoa Road south along Hauraki Road.
Consultation has concluded
Approximately 1347m of watermain including 12 new service connections and valves is being laid from Wharepoa Road south along Hauraki Road.
-
Wood Street, Paeroa - Complete
Share Wood Street, Paeroa - Complete on Facebook Share Wood Street, Paeroa - Complete on Twitter Share Wood Street, Paeroa - Complete on Linkedin Email Wood Street, Paeroa - Complete link
Approximately 183m of new watermain including 12 new service connections and valves has been installed in Wood Street.
Work in this area is now complete.
Consultation has concluded
Approximately 183m of new watermain including 12 new service connections and valves has been installed in Wood Street.
Work in this area is now complete.