Upcoming works on Hauraki Road - Monday 12 May to Friday 30 May 2025

Chipsealing works

‘Chipsealing is scheduled to take place around Wednesday 21st May with the exact date still to be confirmed depending on the weather.

Hauraki Road will be closed to through traffic from 9am until approx. 6pm to allow chipsealing to take place.

During these hours, a temporary detour will be in place, as shown on the map below.

Detour for one day closure for chipsealing works – Wednesday 21st May - to be confirmed

Footpath construction

From Monday 12 May to Friday 30 May, a new footpath will be constructed section by section along the western side of Hauraki Road. Temporary accessways will be maintained at all times for residents to access their properties.

New Vehicle Access Construction

Our contractor will also be creating new vehicle accessways to Hauraki Road, depending on individual property requirements and accessibility. If entrance to your property is impacted, the Camex team will contact you directly.

Line marking

Line marking will be completed approximately 3 days after chipsealing, depending on weather and site conditions.


Thank you for your ongoing patience and understanding as we complete these important works.

Share Upcoming works on Hauraki Road - Monday 12 May to Friday 30 May 2025 on Facebook Share Upcoming works on Hauraki Road - Monday 12 May to Friday 30 May 2025 on Twitter Share Upcoming works on Hauraki Road - Monday 12 May to Friday 30 May 2025 on Linkedin Email Upcoming works on Hauraki Road - Monday 12 May to Friday 30 May 2025 link