Works Update - 15 January 2025

Unfortunately, due to some wet weather our programme of work wasn’t entirely competed before Christmas as planned. Our night works for asphalt in Darlington Street, Ngātea and Seddon Street in Waihi experienced some delays but were completed just in time for Christmas.

Some roads in Ngātea, Paeroa and Waihi were completed in the week starting 6th January. The sweeping and road marking of these streets is still underway.

There will be ongoing monitoring of chipseal sites this month to identify any further sweeping requirements to remove excessive loose chip.

You may notice some paint marks on road around the network, we have been busy scheduling our next year's reseals programme and identifying any repairs needed before then.