Works Update - 22 November 2024

Work has been focused on the Plains rural area over the last 3 weeks.

So far, we've completed 40% of our square metre area planned, or to look at it another way, 15% of the road sections scheduled.

There are still several roads to be affected over the next few months - keep an eye on Antenno for updates!

We also have some night works planned for Darlington Street, Ngātea and Seddon Street, Waihi - depending on weather this work will proceed in early December 2024.