Trig Road North Upgrade

Share Trig Road North Upgrade on Facebook Share Trig Road North Upgrade on Twitter Share Trig Road North Upgrade on Linkedin Email Trig Road North Upgrade link

Road & Culvert Update - January 2026

The new culvert has been completed, and the road is now open in both directions.

Road upgrade works in the area have resumed, with stop/go traffic management in place.

The team is finishing the sub-base and will then apply the basecourse overlay. Weather permitting, the works are expected to be completed by early March.

Thank-you for your continued patience and co-operation while we finish these works.

January 2026 - Road improvements are well underway.

January 2026 - The new culvert.January 2026 - The road over the culvert (due to be marked)

Road & Culvert Update - January 2026

The new culvert has been completed, and the road is now open in both directions.

Road upgrade works in the area have resumed, with stop/go traffic management in place.

The team is finishing the sub-base and will then apply the basecourse overlay. Weather permitting, the works are expected to be completed by early March.

Thank-you for your continued patience and co-operation while we finish these works.

January 2026 - Road improvements are well underway.

January 2026 - The new culvert.January 2026 - The road over the culvert (due to be marked)

  • What's happening with the culvert and the road?

    Share What's happening with the culvert and the road? on Facebook Share What's happening with the culvert and the road? on Twitter Share What's happening with the culvert and the road? on Linkedin Email What's happening with the culvert and the road? link

    Two major improvement projects are taking place on Trig Road North from October 2025.

    Road Rehabilitation

    A 1.5 km stretch of Trig Road North (from property #45 to just before property #186) will be widened from 4.8 metres to 6 metres, creating a safer and more user-friendly route. The work will include:

    • Significant road widening and alignment improvement (including fencing relocation)
    • Installing stormwater drains
    • Building up the road base
    • Final surfacing

    When: Early to mid-October 2025 through to March 2026

    Who’s doing the work: HEB Construction

    Culvert Replacement

    At the same time, we are also replacing an old, corroded culvert, located on Trig Road North around 250m from the Waihi Beach Road intersection. Its replacement will be a new, stronger concrete culvert that ensures the long-term safety and stability of the road. As this culvert carries a tributary of the Ohinemuri River, the stream will need to be temporarily diverted to replace the old culvert with the new one.

    When: Mid-October to early December 2025 (about 8 weeks)

    Who’s doing the work: Ventia

Page last updated: 21 Jan 2026, 11:16 AM