Trig Road North Upgrade

Share Trig Road North Upgrade on Facebook Share Trig Road North Upgrade on Twitter Share Trig Road North Upgrade on Linkedin Email Trig Road North Upgrade link

Road Improvements - Stage 1 Complete

The upgrade works on Trig Road North are now finished. The improvements to this section of the road will help to provide a safer and more reliable route for residents and road users.

This work marks Stage 1 of the planned upgrades for Trig Road North. A further 858 metres of the road is planned to be upgraded in the future, although the timing for this next stage has not yet been confirmed.

Thank-you to residents and road users for your patience and cooperation while the works were underway. Your support has been greatly appreciated while the team carried out these improvements. 🚧👏

Culvert Works Completed

January 2026 - The new culvert.January 2026 - The road over the culvert (due to be marked)

Road Improvements - Stage 1 Complete

The upgrade works on Trig Road North are now finished. The improvements to this section of the road will help to provide a safer and more reliable route for residents and road users.

This work marks Stage 1 of the planned upgrades for Trig Road North. A further 858 metres of the road is planned to be upgraded in the future, although the timing for this next stage has not yet been confirmed.

Thank-you to residents and road users for your patience and cooperation while the works were underway. Your support has been greatly appreciated while the team carried out these improvements. 🚧👏

Culvert Works Completed

January 2026 - The new culvert.January 2026 - The road over the culvert (due to be marked)

  • What's happening with the culvert and the road?

    Share What's happening with the culvert and the road? on Facebook Share What's happening with the culvert and the road? on Twitter Share What's happening with the culvert and the road? on Linkedin Email What's happening with the culvert and the road? link

    Two major improvement projects are taking place on Trig Road North from October 2025.

    Road Rehabilitation

    A 1.5 km stretch of Trig Road North (from property #45 to just before property #186) will be widened from 4.8 metres to 6 metres, creating a safer and more user-friendly route. The work will include:

    • Significant road widening and alignment improvement (including fencing relocation)
    • Installing stormwater drains
    • Building up the road base
    • Final surfacing

    When: Early to mid-October 2025 through to March 2026

    Who’s doing the work: HEB Construction

    Culvert Replacement

    At the same time, we are also replacing an old, corroded culvert, located on Trig Road North around 250m from the Waihi Beach Road intersection. Its replacement will be a new, stronger concrete culvert that ensures the long-term safety and stability of the road. As this culvert carries a tributary of the Ohinemuri River, the stream will need to be temporarily diverted to replace the old culvert with the new one.

    When: Mid-October to early December 2025 (about 8 weeks)

    Who’s doing the work: Ventia