Ngātea North Subdivision - Stage 4

Share Ngātea North Subdivision - Stage 4 on Facebook Share Ngātea North Subdivision - Stage 4 on Twitter Share Ngātea North Subdivision - Stage 4 on Linkedin Email Ngātea North Subdivision - Stage 4 link

Stage 4 is the final stage of land development undertaken by Hauraki District Council in the Ngātea North Subdivision.

5.3 ha of land is being developed into 52 lots for construction of residential homes which face north with views towards the Hauraki Gulf and the Coromandel Peninsula, including the Kaimai Ranges.

Water services, roading detailed design including street lighting, power and telecommunications design have been completed. All necessary consent applications have been granted. Landscape and playground design has been completed.

The subdivision lots should be ready for sale in June/July 2024.


We will be posting regular updates on the Ngātea North Subdivision right here. You can also keep up with the latest news throughout the Hauraki District by signing up for our newsletters.

Stage 4 is the final stage of land development undertaken by Hauraki District Council in the Ngātea North Subdivision.

5.3 ha of land is being developed into 52 lots for construction of residential homes which face north with views towards the Hauraki Gulf and the Coromandel Peninsula, including the Kaimai Ranges.

Water services, roading detailed design including street lighting, power and telecommunications design have been completed. All necessary consent applications have been granted. Landscape and playground design has been completed.

The subdivision lots should be ready for sale in June/July 2024.


We will be posting regular updates on the Ngātea North Subdivision right here. You can also keep up with the latest news throughout the Hauraki District by signing up for our newsletters.

  • Works Update - 3 April 2024

    Share Works Update - 3 April 2024 on Facebook Share Works Update - 3 April 2024 on Twitter Share Works Update - 3 April 2024 on Linkedin Email Works Update - 3 April 2024 link

    Wow! Look at the changes at Ngātea North in 6 months!

    This is the latest drone picture compared to one from October 2023.

    March 2024

    October 2023

    Dempsey Wood Civil Ltd have the project on schedule for the civil works to be completed by June 2024.



  • Works Update - 23 February 2024

    Share Works Update - 23 February 2024 on Facebook Share Works Update - 23 February 2024 on Twitter Share Works Update - 23 February 2024 on Linkedin Email Works Update - 23 February 2024 link

    The latest drone images show the subdivision taking shape. The project is on schedule and the civil works are likely to complete by June 2024.

    Check out our photo gallery to see more pictures.

  • Works Update - 16 January 2024

    Share Works Update - 16 January 2024 on Facebook Share Works Update - 16 January 2024 on Twitter Share Works Update - 16 January 2024 on Linkedin Email Works Update - 16 January 2024 link

    Roads are appearing all over the Ngātea North subdivision. Below is a drone picture taken in early November 2023.



  • Works Progress Update - 1 November 2023

    Share Works Progress Update - 1 November 2023 on Facebook Share Works Progress Update - 1 November 2023 on Twitter Share Works Progress Update - 1 November 2023 on Linkedin Email Works Progress Update - 1 November 2023 link

    Dempsey Wood Civil Ltd have been flat out at Ngātea North, the drainage has now been completed and they are working on the roading.

  • Works Progress Update - 19 October 2023

    Share Works Progress Update - 19 October 2023 on Facebook Share Works Progress Update - 19 October 2023 on Twitter Share Works Progress Update - 19 October 2023 on Linkedin Email Works Progress Update - 19 October 2023 link

    The Ngātea North subdivision is progressing well with Dempsey Wood Civil Ltd on track with this project.

    At the moment they are part way through installing the sewer network.

    Next will be the stormwater network, before they move on to the kerbing and roads, which is when the site will really begin to take shape.

  • Works Progress Update: 15 September 2023

    Share Works Progress Update: 15 September 2023 on Facebook Share Works Progress Update: 15 September 2023 on Twitter Share Works Progress Update: 15 September 2023 on Linkedin Email Works Progress Update: 15 September 2023 link
    supporting image


    Dempsey Wood Civil Ltd have been engaged to carry out the civil works, including connecting storm water, drinking water and wastewater, power and fibre to the sections.

    Work has begun and is likely to be completed by June 2024.


    Our contractors will be working between 8am to 5pm Monday to Friday; and 8am to 2pm on Saturdays.